electric service connection
you know of my father, that the electric service entrance was made today. Sorry civil contractors have not set the phone cord into the house, so that we can dig even a little bit on it already.
We had a bit of the Befürchtnis that the connection to the electric does not work today, as was (probably) filled in the company Innotec for deep drilling of the geothermal heat, the open ditches.
But it's all work, so we have now virtually even electricity in the house. The company has a residential line elnet then switched today and immediately installed two boxes in the utility room, from which we can now tap into electricity first.
In terms of third drainage, which was not connected with on Monday, unfortunately we could not achieve anything. But a good Week, we still have time before the 07.12. started in the utility room with tile heating range is and then at 10.12. to heat.
Thursday, November 25, 2010
Wednesday, November 24, 2010
Wedding Day After Brunch Invitation Wording
tile selection, borehole
Today we were then in Potsdam at Raab Karcher for tile selection. Not so easy. But after nearly 2 hours we had everything we needed and wanted.
After tile selection, we drove past the house and still have a little watched in deep drilling for geothermal heating.
are made 2 holes on the side of the house. Each approx 63m deep.
Thursday is then planned that the electricity is put into the house.
Today we were then in Potsdam at Raab Karcher for tile selection. Not so easy. But after nearly 2 hours we had everything we needed and wanted.
tiles for utility room and hallway | |
floor tiles bathroom |
wall tiles bathroom |
tiled kitchen |
floor tile living room |
After tile selection, we drove past the house and still have a little watched in deep drilling for geothermal heating.
are made 2 holes on the side of the house. Each approx 63m deep.
Thursday is then planned that the electricity is put into the house.
Monday, November 22, 2010
Brine Triumph Xp Helmet Decals
floor, drinking water and sewage
Last week Wednesday was in our house finally poured the cement floor. Now we have to constantly provide good ventilation and hope that soon comes the heater.
These are already taken some important steps, because today on Monday, the potable water moved into the house and prepared the waste water connections. Unfortunately, we missed a connection, so the Re-connecting the kitchen must be rectified.
have for this coming Thursday we will get a short-term connection to the current date, so that we will hopefully release the Baustromanschluss.
also expected to begin on Thursday, the deep drilling for geothermal energy. All in all, an exciting but also exhausting week.
Last week Wednesday was in our house finally poured the cement floor. Now we have to constantly provide good ventilation and hope that soon comes the heater.
These are already taken some important steps, because today on Monday, the potable water moved into the house and prepared the waste water connections. Unfortunately, we missed a connection, so the Re-connecting the kitchen must be rectified.
have for this coming Thursday we will get a short-term connection to the current date, so that we will hopefully release the Baustromanschluss.
also expected to begin on Thursday, the deep drilling for geothermal energy. All in all, an exciting but also exhausting week.
Sunday, November 14, 2010
Nallis Saree House Vancouver
raw installation Plumbing / Heating
Last week was completed, the raw installation of heating and sanitary facilities. In all rooms the floor was laid and preparations were made for the laying of the concrete. This will come in the plan on Tuesday.
Last week was completed, the raw installation of heating and sanitary facilities. In all rooms the floor was laid and preparations were made for the laying of the concrete. This will come in the plan on Tuesday.
bedroom |
children |
hallway floor |
corridor EC |
next guest rooms, guest WC front |
HWR |
kitchen |
outdoor faucet flush |
The finished downpipe on Input |
Saturday, November 6, 2010
Welcome To My Marriage Messages
Buntseinputz, plastering, raw installation Plumbing / Heating
Last week the company has made Hansen the mottled stone wall in our house. This worked perfectly straightforward and very clean and fast. Moreover, since the skeleton was also removed, we can see the house now in full bloom.
Since last Wednesday is now the attachments plaster finish - almost 2 weeks later than planned. But with the result, we're quite happy.
Dörau The company began last Thursday with the raw installation of heating and plumbing. Already beeidruckend how to change the rooms.
Next week includes the company Dörau then the raw installation the sanitary and heating from. But first we have on Monday a few inconsistencies with the way the outside water faucet and the position of the toilet in the floor vote.
Last week the company has made Hansen the mottled stone wall in our house. This worked perfectly straightforward and very clean and fast. Moreover, since the skeleton was also removed, we can see the house now in full bloom.
Our house from the front - finally without scaffolding, but now with colored stone plaster |
Detail of colored stone plaster |
view from the southwest |
Since last Wednesday is now the attachments plaster finish - almost 2 weeks later than planned. But with the result, we're quite happy.
guest bathroom and plastered with raw installation of the cistern |
The hall is now plastered. |
Dörau The company began last Thursday with the raw installation of heating and plumbing. Already beeidruckend how to change the rooms.
In the Bedroom takes the form of laying the underfloor heating. |
Next week includes the company Dörau then the raw installation the sanitary and heating from. But first we have on Monday a few inconsistencies with the way the outside water faucet and the position of the toilet in the floor vote.
Subscribe to:
Posts (Atom)